Comrade Nguyen Van Son, Deputy Secretary of the Provincial Party Committee, Chairman of the Provincial People's Committee, Head of the Steering Committee for National Target Programs of the province for the period 2021 - 2025 attended and chaired the conference.
Conference of the Steering Committee of National Target Programs of Tuyen Quang province for the period 2021-2025. Photo: Thanh Phuc
Attending the conference were comrades: Van Dinh Thao, member of the Provincial Party Standing Committee, Director of the Department of Planning and Investment; Nguyen The Giang, member of the Provincial Party Committee, Vice Chairman of the Provincial People's Committee; Hoang Viet Phuong, member of the Provincial Party Committee, Vice Chairman of the Provincial People's Committee; members of the Steering Committee for National Target Programs of the province.
Speaking at the conference, Chairman of the Provincial People's Committee Nguyen Van Son emphasized that the reason for the slow disbursement progress of the 3 National Target Programs in the province is due to the lack of initiative and focus in the direction and management of local leaders, agencies and units, and some of the Central Government's guiding documents are not complete. He requested that delegates need to assess and look directly at the difficulties and limitations in order to find solutions to remove them and speed up the disbursement progress in the coming time.
Chairman of the Provincial People's Committee Nguyen Van Son delivered a concluding speech at the conference. Photo: Thanh Phuc
The Provincial Party Committee and Provincial People's Committee have issued many documents directing and urging the acceleration of progress and disbursement of capital for National Target Programs. However, the implementation at the grassroots level is still confusing, the progress of implementation and disbursement is very slow, many contents, works and projects have not yet disbursed the assigned capital.
In 2024, the total allocated State budget capital plan is over 1,300 billion VND. From January 1, 2024 to April 30, 2024, the total disbursed State budget capital in 2024 reached over 159 billion VND, reaching 9.68% of the capital disbursement plan in 2024, the capital in 2023 extended to 2024, the new disbursement rate reached 10.18% of the plan. Of which, Na Hang district achieved 21.5% of the plan, Ham Yen district achieved 16.34% of the plan, Son Duong district achieved 12.14% of the plan, Yen Son district achieved 11.49% of the plan, Chiem Hoa district achieved 11.4% of the plan, Lam Binh district achieved 7.6% of the plan, Tuyen Quang city achieved 0.69% of the plan, provincial departments and branches disbursed 1.21% of the plan.
Leaders of the Provincial People's Committee and provincial departments and branches attended the conference. Photo: Thanh Phuc
Regarding the disbursement of planned capital in 2024 according to each national target program: The national target program on new rural construction disbursed 2.29% of the plan, the national target program on socio-economic development in ethnic minority and mountainous areas, the disbursement rate reached 13.8% of the plan; the national target program on sustainable poverty reduction, the disbursement rate reached 7.25% of the plan.
Discussing at the conference, leaders of districts, agencies and units clarified the causes, difficulties and obstacles affecting the disbursement progress. At the same time, they also proposed solutions and methods to speed up the implementation and disbursement progress of the National Target Programs. Accordingly, the solutions discussed and debated are: For the People's Committees of districts and cities, agencies and units assigned capital to implement the programs, it is necessary to promptly remove difficulties and obstacles; develop an implementation roadmap and assign specific tasks associated with the responsibilities of the heads in case of slow disbursement; prioritize capital allocation for projects with feasibility in terms of investment procedures, implementation and disbursement, and not to allow debt to arise in basic construction. The agencies in charge of the program should strengthen coordination with relevant agencies and units to review and propose solutions to completely resolve difficulties and obstacles...
Concluding the conference, Chairman of the Provincial People's Committee Nguyen Van Son affirmed that in the first 5 months of the year, the province has resolved many difficulties and obstacles in implementing the National Target Programs. However, the disbursement progress of the National Target Programs in 2024 is currently very slow.
To successfully implement the plan and comply with regulations in implementing the National Target Programs, he requested that heads of departments, branches, and sectors, and Chairmen of People's Committees of districts and cities be responsible for implementing and closely coordinating with relevant agencies to accelerate the implementation progress and disburse capital in a drastic, proactive, and timely manner to remove difficulties and obstacles, comply with the plan and roadmap for each month and each quarter; assign specific tasks to each individual, and attach responsibility to the head.
Delegates attending the conference. Photo: Thanh Phuc
By the end of May 2024, agencies, units and localities must complete the adjustment of capital sources from component projects that are no longer supported, do not meet the disbursement conditions according to regulations or have low disbursement rates to supplement the implementation estimates for other component projects with high disbursement potential. By the end of June 2024, the programs must be signed contracts and the disbursement rate of the programs must reach 40% of the plan. By the end of September, the disbursement rate of the programs must reach 75% of the plan and strive to reach over 95% of the assigned capital plan by the end of December 2024 in accordance with the direction in Conclusion No. 1525-KL/TU dated March 15, 2024 of the Provincial Party Standing Committee.
He requested that agencies, units and localities continue to actively implement Resolution No. 111/2024/QH15 of the National Assembly on a number of specific mechanisms and policies to implement the National Target Programs. The Chairman of the Provincial People's Committee noted that corruption, waste and profiteering must absolutely not occur in the process of implementing the programs. Members of the Provincial Steering Committee for National Target Programs must promote their assigned roles and responsibilities and take charge of districts and cities.
For the agencies in charge of implementing the programs, they must grasp the progress of implementation, closely coordinate with districts and cities to promptly remove difficulties and obstacles. He emphasized that the work of supervision, inspection and urging must be carried out regularly, in accordance with the direction of Prime Minister Pham Minh Chinh "overcoming the sun and overcoming the rain", "through holidays and Tet", "only discuss work, no backtracking".