According to the plan, in 2025, Binh Duong Power Company will implement 9 110kV projects with a total additional capacity of 584 MVA; in which it strives to complete and put into operation a number of key projects before April 30, such as: Cong Xanh 110kV Station and connecting line; VSIP 2 MR2 Station and connecting line; Thanh An - Ben Cat 110kV Line; Thanh Phuoc 110kV Station and connecting line; An Lap 110kV Station...
H. ANH
Source: https://baobinhduong.vn/cong-ty-dien-luc-binh-duong-phan-dau-dua-vao-van-hanh-mot-so-cong-trinh-truoc-ngay-30-4-a344467.html