Basically completed loading Can Tho highway

Báo Xây dựngBáo Xây dựng21/03/2025

The Can Tho - Ca Mau Expressway is in the final stage, requiring contractors to be proactive in materials, increase equipment, machinery, and workers to ensure compliance with the approved construction plan.


On March 21, My Thuan Project Management Board inspected and urged the construction progress and the implementation of the pilot project, forced loading by heavy trucks of the North-South expressway project phase 2021-2025, Can Tho - Ca Mau section.

Cơ bản hoàn thành gia tải cao tốc Cần Thơ - Cà Mau trong tháng 3- Ảnh 1.

Construction of IC2 intersection belongs to Can Tho - Hau Giang component project.

According to the My Thuan Project Management Board, the total construction output of the project has reached 62.1%. Contractors have treated weak soil according to the loading plan for more than 84.21km. Of which, the Can Tho - Hau Giang section is more than 32.61km, the Hau Giang - Ca Mau section is more than 51.6km.

Regarding bridges, 63 bridges have completed their decks, of which 12 are open to technical traffic.

My Thuan Project Management Board and contractors strive to complete concrete decks of the remaining 34 bridges by April 30.

For the main route, in March 2025, the loading work will be basically completed and the first section will begin unloading. From here, contractors will carry out the construction of the road surface structure in parallel with the unloading of the sections. By December 31, the entire main route will be completed.

Cơ bản hoàn thành gia tải cao tốc Cần Thơ - Cà Mau trong tháng 3- Ảnh 2.

Construction of Kenh Sang Bridge under the Hau Giang - Ca Mau component project

Also according to the My Thuan Project Management Board, implementing the direction of the Ministry of Transport, now the Ministry of Construction, the unit has organized the implementation of pilot work, forced loading by a convoy of heavy trucks on the roadbed waiting to subside, treating weak soil with wicks combined with pre-loading.

The pilot section from Km58+200 - Km58+600 belongs to the Hau Giang - Ca Mau component project. Of which, 200m of the route does not have a forced loading pilot to serve as a comparison section.

Through actual inspection, My Thuan Project Management Board requested contractors to urgently mobilize enough crushed stone aggregate to the construction site before June 30 to proactively provide materials, increase equipment, machinery, and workers to ensure compliance with the approved construction plan.

Cơ bản hoàn thành gia tải cao tốc Cần Thơ - Cà Mau trong tháng 3- Ảnh 3.

Pilot forced loading by truckload train.

At the same time, the construction team will work overtime to complete the asphalt, expansion joints and bridgeheads of the bridges on the route, ensuring the goal of opening the entire main route by April 30. For sections that are eligible for unloading, the construction will be carried out in a rolling manner, and the road surface foundation will be completed while the traffic safety system and median strip are completed.

Regarding the pilot forced loading by heavy truck convoy, My Thuan Project Management Board said that it will continue to coordinate with the unit that drafted the outline, the monitoring unit, and the pilot construction unit to continue reviewing the pilot results and report to the Ministry of Construction.

The Can Tho - Ca Mau Expressway is over 110km long, with a total investment of over VND27,500 billion. It is divided into two sub-projects, of which the Can Tho - Hau Giang section is over 37km long, with a total investment of over VND10,370 billion. The Hau Giang - Ca Mau section is over 73km long, with a total investment of over VND17,152 billion.

Construction started in January 2023. The project is in the acceleration phase to complete the target in 2025 as directed by the Prime Minister.



Source: https://www.baogiaothong.vn/co-ban-hoan-thanh-gia-tai-cao-toc-can-tho-ca-mau-trong-thang-3-2025-192250321160259189.htm

Comment (0)

No data
No data

Same tag

Same category

4th time seeing Ba Den mountain clearly and rarely from Ho Chi Minh City
Feast your eyes on the beautiful scenery of Vietnam in Soobin's MV Muc Ha Vo Nhan
Coffee shops with early Christmas decorations make sales soar, attracting many young people
What is special about the island near the maritime border with China?

Same author

Heritage

Figure

Enterprise

Admiring the national costumes of 80 beauties competing in Miss International 2025 in Japan

News

Political System

Destination

Product