Vietnam.vn - Nền tảng quảng bá Việt Nam

Basically completed loading Can Tho highway

Báo Xây dựngBáo Xây dựng21/03/2025

The Can Tho - Ca Mau expressway is in its final stages, requiring contractors to proactively secure materials, increase equipment, machinery, and workers to ensure the construction proceeds according to the approved schedule.


On March 21st, the My Thuan Project Management Board inspected and urged the progress of construction and the implementation of the pilot project of forced loading using heavy trucks on the North-South Expressway project, phase 2021-2025, Can Tho - Ca Mau section.

Cơ bản hoàn thành gia tải cao tốc Cần Thơ - Cà Mau trong tháng 3- Ảnh 1.

Construction work on the IC2 interchange is part of the Can Tho -Hau Giang component project.

According to the My Thuan Project Management Board, the overall project construction progress has reached 62.1%. Contractors have treated weak soil using the preloading method for more than 84.21 km. This includes over 32.61 km of the Can Tho - Hau Giang section and over 51.6 km of the Hau Giang - Ca Mau section.

Regarding bridges, 63 bridges have had their decks completed, of which 12 are open for technical traffic.

The My Thuan Project Management Board and contractors are striving to complete the concrete paving of the remaining 34 bridges by April 30th.

For the main route, the preloading work will be basically completed in March 2025, and the first section will begin to be unloaded. From there, contractors will proceed with the phased construction of the road surface structure in parallel with the unloading of the sections. The entire main route will be completed by December 31st.

Cơ bản hoàn thành gia tải cao tốc Cần Thơ - Cà Mau trong tháng 3- Ảnh 2.

Construction of the Kênh Sáng bridge is part of the Hậu Giang-Cà Mau component project.

According to the My Thuan Project Management Board, following the directives of the Ministry of Transport (now the Ministry of Construction), the unit has organized and implemented a pilot project involving forced loading using heavy trucks on the roadbed awaiting settlement, treating weak soil with drainage wicks combined with pre-loading.

The pilot section from Km58+200 to Km58+600 is part of the Hau Giang-Ca Mau component project. Of this, 200m of the route will not undergo forced loading as a comparison section.

Following an on-site inspection, the My Thuan Project Management Board requested contractors to urgently mobilize sufficient quantities of crushed stone aggregate to the construction site before June 30th to ensure material availability, increase equipment, machinery, and workers to guarantee the approved construction schedule.

Cơ bản hoàn thành gia tải cao tốc Cần Thơ - Cà Mau trong tháng 3- Ảnh 3.

Pilot program for forced loading using a convoy of heavy trucks.

Simultaneously, overtime and shift work will be organized to complete the asphalt paving, expansion joints, and bridge abutment construction on the bridges along the route, ensuring the goal of opening the entire main route by April 30th. For sections that are ready for load removal, construction will be carried out in a phased manner, completing the road foundation and surface construction while simultaneously finishing the traffic safety system and median strips.

Regarding the pilot project for forced loading using heavy truck convoys, the My Thuan Project Management Board stated that it will continue to coordinate with the project planning unit, the supervisory unit, and the pilot construction unit to review the pilot results and submit a report to the Ministry of Construction.

The Can Tho-Ca Mau Expressway is over 110km long, with a total investment of over 27,500 billion VND. It is divided into two component projects: the Can Tho-Hau Giang section is over 37km long with a total investment of over 10,370 billion VND, and the Hau Giang-Ca Mau section is over 73km long with a total investment of over 17,152 billion VND.

Construction began in January 2023. The project is currently in an accelerated phase to achieve its target completion date in 2025, as directed by the Prime Minister.



Source: https://www.baogiaothong.vn/co-ban-hoan-thanh-gia-tai-cao-toc-can-tho-ca-mau-trong-thang-3-2025-192250321160259189.htm

Comment (0)

Please leave a comment to share your feelings!

Same tag

Same category

Christmas entertainment spot causing a stir among young people in Ho Chi Minh City with a 7m pine tree
What's in the 100m alley that's causing a stir at Christmas?
Overwhelmed by the super wedding held for 7 days and nights in Phu Quoc
Ancient Costume Parade: A Hundred Flowers Joy

Same author

Heritage

Figure

Enterprise

Vietnam is the world's leading Heritage Destination in 2025

News

Political System

Destination

Product