Today (November 30), Mr. Tran Van Thi - Director of My Thuan Project Management Board - said that the bottleneck in the site clearance at component project 1A of the Tan Van - Nhon Trach section construction investment project (phase 1) of Ho Chi Minh City Ring Road 3 has been resolved.

Specifically, Ho Chi Minh City has handed over 100% of the area. Meanwhile, in Dong Nai, the construction unit has accessed 49.21/49.30 hectares, equivalent to 99.82% of the area.

z6084050924375_8795f700865e043b2534088650345594.jpg
The main route on the Dong Nai side of the Nhon Trach bridge approach road construction package has been basically 100% handed over. Photo: TK

“Thus, the main route has been basically handed over 100%. In addition, the project has 7 public works locations and 6 have been relocated. The remaining locations are expected to be completed in December,” Mr. Thi informed.

Regarding implementation progress, component project 1A started on September 24, 2022, with the contract completion date in September 2025.

The project has 2 packages: CW1 - construction of Nhon Trach bridge, the largest bridge on Ho Chi Minh City's Ring Road 3 with a length of 2,600m, worth 1,618 billion VND; CW2 package - construction of approach roads at both ends of the bridge, 5,620m long, worth 1,071 billion VND.

Dong Nai bridge 77977 121253.jpg
Nhon Trach Bridge will be completed 4 months ahead of schedule. Photo: Dao Phuong

According to Mr. Thi, the total construction volume of the project has reached 76%. The contractor is striving to shorten the progress to complete the project by April 30, 2025, 4 months ahead of schedule.

Component project 1A Tan Van - Nhon Trach is about 8.22km long, of which 6.3km runs through Dong Nai and 1.92km runs through Ho Chi Minh City with an investment cost of more than VND6,900 billion from Korean ODA loans and Vietnam's counterpart funds.

On the route, there are 2 bridges over the river (Rach Chay bridge is 280m long and Nhon Trach bridge is 2,040m long), 4 overpasses on the approach roads at the intersection with Ho Chi Minh City - Long Thanh - Dau Giay expressway with a total length of about 3,788m.

Construction of Nhon Trach bridge connecting Ho Chi Minh City with Dong Nai started on September 24.

Construction of Nhon Trach bridge connecting Ho Chi Minh City with Dong Nai started on September 24.

After many delays, Project 1A of Ring Road 3 will start construction on September 24, including an important item of building Nhon Trach Bridge connecting Ho Chi Minh City with Dong Nai.
Ho Chi Minh City Ring Road 3: No delay to open the entire route to traffic on April 30, 2026

Ho Chi Minh City Ring Road 3: No delay to open the entire route to traffic on April 30, 2026

The investor is required to carry out the work with the spirit of working through the Tet holiday, only working, no backtracking... determined to open the entire Ho Chi Minh City Ring Road 3 to traffic on April 30, 2026.
The largest bridge of the Ho Chi Minh City Ring Road 3 project is accelerating its completion.

The largest bridge of the Ho Chi Minh City Ring Road 3 project is accelerating its completion.

The construction site of Nhon Trach Bridge (the largest bridge in Ho Chi Minh City's Ring Road 3) is speeding up construction in 3 shifts and 4 crews to complete the entire main span by the end of this year.