After completing about 200m of quality testing, the contractor will mass-pave the Bien Hoa - Vung Tau highway, through Dong Nai.
Bien Hoa - Vung Tau Expressway through Dong Nai begins to lay the first layer of asphalt - Photo: A LOC
On January 15, the joint venture contractor for package 21 (component project 1, Bien Hoa - Vung Tau expressway) laid the first layer of asphalt concrete.
Accordingly, the location of the plastic carpet in An Phuoc commune, Long Thanh district is undertaken by Lizen Joint Stock Company.
According to the contractor representative, the asphalt section is expected to be nearly 4km long, but first 200m will be constructed for quality testing.
About three days after the inspection is completed, the contractor will start mass construction and expects to have about 1km of asphalt paved before Tet.
Mr. Tran Van Huyen, executive director of the joint venture contractor for package 21, said that to speed up the progress, the unit mobilized all human resources and equipment to work in 3 shifts, 4 shifts continuously day and night.
Currently, the section of the route undertaken by Lizen Joint Stock Company has basically had enough land and fill, so the contractor is speeding up construction.
According to the Dong Nai Traffic Construction Project Management Board (the investor), the 16km long component project 1 includes two main bid packages.
After checking the quality, the contractor will mass-pave a nearly 4km long section of the route, passing through Long Thanh district, Dong Nai - Photo: A LOC
Up to now, component project 1 has handed over about 104.16 hectares, reaching 76% of the area to be handed over.
The joint venture contractor has organized 20 construction teams, mobilized 200 machines and equipment, nearly 400 engineers and workers to work urgently. However, due to limited space, the output has only reached nearly 20%.
Total investment in Bien Hoa - Vung Tau expressway expected to increase by 5,400 billion VND
The Bien Hoa - Vung Tau Expressway project is 53.7km long, passing through Ba Ria - Vung Tau and Dong Nai, with phase 1 having 4 to 6 lanes. The project started construction in mid-June 2023 with a total investment of more than 17,800 billion VND.
In a recent report sent to the National Assembly, the cost of site clearance for component projects is expected to increase by about VND3,267 billion compared to the total investment approved by the National Assembly.
In which, component project 1 increased by 120 billion VND, component project 2 increased by 1,272 billion VND, component project 3 increased by 1,875 billion VND.
In addition, in component project 3, the People's Committee of Ba Ria - Vung Tau province proposed to add the My Xuan - Ngai Giao intersection (intersection with provincial road 991) with an estimated cost of about 1,581 billion VND to improve transport capacity, connecting Cai Mep - Thi Vai port area with Long Thanh airport.
Thus, the total investment of the Bien Hoa - Vung Tau expressway project is expected to increase by about 5,400 billion VND compared to the approved total investment.
Source: https://tuoitre.vn/cao-toc-bien-hoa-vung-tau-doan-qua-dong-nai-bat-dau-tham-nhua-20250115163219874.htm