Close-up of the 575 billion VND highway connecting project in Ha Tinh asking for a progress extension

Báo Giao thôngBáo Giao thông02/12/2024

The Ham Nghi road extension project (Ha Tinh city) connecting with the expressway and high-speed railway station with a total cost of 575 billion VND is asking for an extension due to a residential area.


The reason why 100% of the land cannot be handed over is due to the slow land price determination and the time it takes to determine the appraisal unit and approve the construction of the resettlement area.

According to the leader of the Department of Natural Resources and Environment, land recovery is carried out after handing over resettlement land in the field to people subject to resettlement, so it is necessary to invest in building resettlement areas before land recovery.

In addition, the change in compensation policy for garden land adjacent to residential land also encountered some difficulties. Previously, garden land would be compensated 50%, but according to the new law, garden land will not be compensated. If garden land is not compensated, households will not agree because it greatly affects people's rights.

It is expected that by June 2025, after the contractor selection is completed, construction of the resettlement area for the Ham Nghi extended road project will begin.



Source: https://www.baogiaothong.vn/can-canh-du-an-duong-noi-cao-toc-575-ty-dong-o-ha-tinh-xin-gia-han-tien-do-192241202184503198.htm

Comment (0)

No data
No data

Same tag

Same category

Wandering around Lach Bang beach village
Explore Tuy Phong color palette
Hue - The capital of the five-panel ao dai
Colorful Vietnamese landscapes through the lens of photographer Khanh Phan

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product