Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Việt NamViệt Nam29/07/2024


On July 29, Comrade Do Trong Hung, Member of the Party Central Committee, Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council inspected the construction progress of a number of key projects in Hoang Hoa and Nga Son districts, including: Xuan Quang Bridge construction project under the project connecting National Highway 1A with National Highway 45 from Hoang Xuan commune, Hoang Hoa district to Thieu Long commune, Thieu Hoa district; Nga Son - Hoang Hoa coastal road; Traffic project from Bim Son Industrial Park to Nga Son - Hoang Hoa coastal road.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung listened to the contractor's report on the construction progress of Xuan Quang bridge, part of the project connecting National Highway 1A with National Highway 45 from Hoang Xuan commune, Hoang Hoa district to Thieu Long commune, Thieu Hoa district.

Accompanying him were comrade Mai Xuan Liem, member of the Provincial Party Standing Committee, Vice Chairman of the Provincial People's Committee; leaders of the Provincial Party Office and a number of provincial-level departments; leaders of Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung and the working delegation inspected the construction of Xuan Quang bridge under the project connecting National Highway 1A with National Highway 45 from Hoang Xuan commune, Hoang Hoa district to Thieu Long commune, Thieu Hoa district.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Xuan Quang Bridge is being constructed by the contractor.

According to the report of the Provincial Traffic Construction Investment Project Management Board (PMU), up to now, the project has achieved 73% of the volume. In Notice No. 414-TB/VPTU, dated April 10, 2024 of the Provincial Party Committee Office and the direction of the Provincial People's Committee Chairman at the launching ceremony in early 2024, the investor is required to strive to close Xuan Quang Bridge in early August 2024 and complete the remaining items of the project in October 2024.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung listened to the contractor report on the construction progress of Xuan Quang bridge.

Following the direction of the provincial leaders, the Project Management Board has approved the adjustment of the detailed construction schedule and the contractor has signed a commitment to complete the project by October 2024. However, in reality, up to this point, the progress is difficult to complete as committed; specifically, if the contractor increases enough human resources and equipment, the construction progress will still be 20 days behind schedule.

After checking and listening to the contractor's report, Provincial Party Secretary Do Trong Hung stated: The North-South Expressway passing through Thanh Hoa province has 7 intersections, including Thieu Giang intersection, the third intersection, which is very important in creating conditions for socio-economic development in the northeastern localities of the province; the road connecting National Highway 1A with National Highway 45, including Xuan Quang Bridge, is a road with the goal of connecting inter-regional areas including Vinh Loc, Yen Dinh, Thieu Hoa and part of Dong Son district... The completion of the road connecting National Highway 1A with National Highway 45 from Hoang Xuan commune, Hoang Hoa district to Thieu Long commune, Thieu Hoa district will reduce the traffic density at Dong Xuan intersection. Therefore, it is necessary to complete it soon to promote the effectiveness of the road, contributing to the socio-economic development of the province.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung presents gifts to cadres and engineers constructing Xuan Quang bridge.

Based on the field inspection, Provincial Party Secretary Do Trong Hung highly appreciated the provincial departments, functional branches and the Party Committees and authorities of Hoang Hoa and Thieu Hoa districts, as well as the contractors for their efforts in implementing the project.

However, in response to the requirements of faster and more sustainable development of the province, Provincial Party Secretary Do Trong Hung requested that in the coming time, the Department of Transport, the Project Management Board and the Party Committees and authorities with projects passing through need to continue to focus on removing difficulties and obstacles so that the project can be put into use soon. For the contractor, it is necessary to focus all resources on human resources and equipment to construct and strive to organize the inauguration and technical traffic opening by October 25, 2024, which will be a project to celebrate the 70th anniversary of welcoming compatriots, cadres, soldiers and students from the South to the North.

Provincial Party Secretary Do Trong Hung also noted that, in addition to ensuring progress, the contractor must ensure safety, quality, technique, and aesthetics of the project; the Party Committee and government of Hoang Hoa district need to ensure security, order, landscape, and space of the green - clean - beautiful, environmentally friendly route.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung and members of the inspection delegation of the Coastal Road Project, Nga Son - Hoang Hoa section.

Immediately after checking the construction progress of Xuan Quang bridge, Provincial Party Secretary Do Trong Hung and members of the delegation inspected the Coastal Road Project from Nga Son to Hoang Hoa; the traffic project from Bim Son Industrial Park to the Nga Son - Hoang Hoa coastal road.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

According to the report of the Project Management Board, on January 4, 2024, the Provincial Party Committee Office issued Notice No. 280/TB-VPTU announcing the conclusion of Comrade Do Trong Hung, Member of the Party Central Committee, Secretary of the Provincial Party Committee, Chairman of the Provincial People's Council at the inspection of a number of key traffic works and projects; in which, for the Coastal Road Project, Nga Son - Hoang Hoa section, the contractor was required to mobilize the highest human resources, machinery, equipment, materials, and add more construction teams to speed up the project implementation progress, striving to complete the roadbed before June 30, 2024. However, the two main contractors constructing the road, Cuong Thinh Thi Construction Investment Group Joint Stock Company and Mien Trung Construction Group Joint Stock Company, still did not seriously implement the instructions and conclusions of the Provincial Party Committee in focusing on speeding up the construction progress, leading to the project's progress being delayed, unable to complete the roadbed before the above deadline.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung inspected the traffic project from Bim Son Industrial Park to the Nga Son - Hoang Hoa coastal road.

Regarding the Traffic Road Project from Bim Son Industrial Park to the coastal road section Nga Son - Hoang Hoa, up to now in Nga Son district there are still 831m of uncleared land.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

Provincial Party Secretary Do Trong Hung delivered a concluding speech at the working session with leaders, departments, branches, localities, and contractors.

After the field inspection, Provincial Party Secretary Do Trong Hung had a meeting with leaders of departments, branches, localities, contractors and severely criticized contractors and localities for slow progress. At the same time, he highlighted the important role of the coastal route in the socio-economic development of the province and the country.

In response to the requirements for the province's development in the coming time, Provincial Party Secretary Do Trong Hung requested the Party Committee and authorities of Nga Son district to focus on leading, directing, propagating, educating, and mobilizing people affected by the project to agree with the site clearance plan; along with that, fully implementing the State's regimes and policies, ensuring the legitimate rights and interests of the people. The Provincial Party Secretary also requested that Nga Son district, in addition to propagating and mobilizing, if there are cases of intentional non-compliance, must resolutely carry out enforcement so that the project can be implemented, ensuring site clearance before September 2, 2024.

Provincial Party Secretary Do Trong Hung inspected key projects in Hoang Hoa and Nga Son districts.

The Provincial Party Secretary also requested the Provincial People's Committee to direct relevant departments and branches to thoroughly resolve procedures related to construction materials, especially the source of soil and sand for site leveling to ensure the supply of materials for projects. The Provincial People's Committee also directed the Nga Son District People's Committee and relevant departments to remove difficulties in capital sources for site clearance of the project; the investor coordinates with contractors to rebuild the progress of the Nga Son - Hoang Hoa coastal road project. The leaders of the Provincial People's Committee directed departments, branches and localities to strengthen coordination to remove difficulties according to their functions and tasks with the spirit of all for the common benefit, for the development of the province.

Minh Hieu



Source: https://baothanhhoa.vn/bi-thu-tinh-uy-do-trong-hung-kiem-tra-cac-cong-trinh-trong-diem-tai-huyen-hoang-hoa-va-nga-son-220737.htm

Comment (0)

No data
No data

Same tag

Same category

Indonesia fired 7 cannon shots to welcome General Secretary To Lam and his wife.
Admire the state-of-the-art equipment and armored vehicles displayed by the Ministry of Public Security on the streets of Hanoi
“Tunnel: Sun in the Dark”: The first revolutionary film without state funding
Thousands of people in Ho Chi Minh City wait to take Metro Line 1 on its inauguration day.

Same author

Heritage

Figure

Business

No videos available

News

Ministry - Branch

Local

Product