This morning, March 7, the Economic - Budget Committee (KT-NS) of the Provincial People's Council worked with the Provincial Economic Zone Management Board on the results of allocation, management, use of capital sources and progress of implementation of basic construction investment projects/works in 2024 (cumulatively up to the end of 2023) approved by the Provincial People's Council in Resolution No. 69/NQ-HDND dated August 4, 2023; Resolution No. 111/NQ -HDND dated December 7, 2023; Resolution No. 132/NQ -HDND dated December 19, 2023 of the Provincial People's Council assigned by the Provincial People's Committee to localities and units to manage projects or act as investors. Standing Vice Chairman of the Provincial People's Council Nguyen Chien Thang attended the meeting.
The Provincial People's Council's Economic and Human Resources Committee visited the My Thuy Port Project - Photo: HA
According to the report of the Provincial Economic Zone Management Board, in Resolution No. 111/NQ - HDB dated December 7, 2023, there are projects such as: Road project connecting Dong Nam Quang Tri Industrial Park to Cua Viet Port, up to now, the project has package No. 10 which has been fully funded but is still stuck in site clearance so it cannot continue to be implemented... The project of leveling and technical infrastructure in the central area of La Lay border gate was approved with a total investment of 108 billion VND; the project implementation progress is 2021-2024. Currently, the items have been completed.
The 0.95-hectare waiting area for leveling is awaiting a license for mass blasting from the General Department of Defense Industry and is expected to begin mass blasting in the second half of March 2024.
The feasibility study report of the RD 01 and RD 04 projects in Quan Ngang Industrial Park was approved by the Provincial People's Committee in Decision No. 3183/QD-UBND dated December 25, 2023 with a total investment of VND 25 billion; implementation period from 2023 to 2025. Because the capital was allocated at the end of 2023, the project has only disbursed consulting costs and other investment preparation costs.
In Resolution No. 132/NQ-HDND dated December 19, 2023 of the Provincial People's Council, there are 2 projects adjusting the capital reduction of the medium-term plan for 2021-2025, which are the project of clearing bombs, mines and explosives in the resettlement areas of Trieu Phong and Hai Lang districts; the project of the resettlement area of Hai Khe commune and the road to the resettlement area (phase 1). These 2 projects have been completed and the project settlement has been completed, so the medium-term capital has been adjusted to decrease according to the completed value.
The implementation of some projects (not using public investment capital) in industrial parks and economic zones in the province, such as the My Thuy Port Project, has so far encountered some difficulties and problems related to the documents on the transfer of sea area, location of dumping dredged material and use of dredged material, exploitation of planted forest timber, dredging plan for water areas, ship turning basins, mineral recovery within the project scope, site clearance, resettlement, etc.
The project to invest in construction and business of infrastructure of Trieu Phu multi-industry industrial park, up to now, the project has basically completed the procedures for establishing the industrial park, dossiers for changing the purpose of forest use; planning and land use plan...
Quang Tri Industrial Park Project, up to now, the site clearance work in some areas (about 1.9 ha) has issued a decision approving the compensation and support plan, but the people have not yet agreed; the wastewater discharge point of the project is outside the scope of the project, so there are problems in granting construction permits that do not meet the prescribed conditions; the progress of construction of water supply works for the project is slow, affecting the investment activities in building technical infrastructure and attracting investment of investors...
The project to invest in the construction and business of infrastructure of the Tay Bac Ho Xa Industrial Park, up to now, the site clearance work has encountered certain difficulties and obstacles. Although the investor has made great efforts to coordinate with departments, branches and localities to resolve them, it was not until mid-2023 that the difficulties and obstacles were basically resolved, which has affected the progress of the project implementation...
The Provincial Economic Zone Management Board has proposed to the Economic and Financial Committee of the Provincial People's Council issues regarding basic construction investment projects/works in 2024 (cumulatively up to the end of 2023) approved by the Provincial People's Council in Resolution No. 69/NQ-HDND dated August 4, 2023; Resolution No. 111/NQ-HDND dated December 7, 2023.
Resolution No. 132/NQ-HDND dated December 19, 2023 of the Provincial People's Council was assigned by the Provincial People's Committee to localities, project management units or investors such as: Strengthening land management and use in localities; considering and periodically adjusting unit prices of architectural objects and crops to suit and be close to reality; focusing on solving site clearance, compensation, and resettlement support; updating and adjusting the announcement of construction material prices and construction price indexes to meet the requirements of construction investment cost management; controlling fluctuations in construction material prices and strictly handling acts of speculation and price hikes for profiteering...
On the same day, the Provincial People's Council's Economic and Human Resources Committee conducted a field survey of the Trieu Phu Multi-Industry Industrial Park Infrastructure Investment and Business Project, My Thuy Port Project, and the Resettlement Area Infrastructure Construction Project serving the Southeast Quang Tri Economic Zone.
Speaking at the projects that the Provincial People's Council's Economic and Technical Committee had surveyed, Standing Vice Chairman of the Provincial People's Council Nguyen Chien Thang requested the Provincial Economic Zone Management Board to proactively coordinate closely with departments, branches, sectors and localities to do a good job of site clearance; focus human resources to completely resolve problems to ensure the progress of project implementation. There should be a specific plan on the location of dumping dredged material and the use of dredged material to release the volume of waste for the My Thuy Port Project.
Regarding the recommendations, the Provincial People's Council's Economic and Financial Committee will take note, consider and recommend to competent authorities for resolution in the coming time.
Hai An