Vietnam.vn - Nền tảng quảng bá Việt Nam

[Photo] In the "remote mountains" a highway is being built connecting the forest and the sea.

Việt NamViệt Nam21/06/2024


NDO – Of the 3 component projects, Component Project 2, Khanh Hoa-Buon Ma Thuot Expressway from Km 32+000-Km 69+500 with a length of about 37.5km in the territory of Khanh Hoa and Dak Lak provinces, managed by the Ministry of Transport, has the most complex terrain with many high hills and deep ravines, causing construction work to face many difficulties.

The project is divided into 3 component projects. Component project 1 from Km 0+000-Km 32+000 with a length of about 32km in Khanh Hoa province, with a total investment of 5,632 billion VND, with the People's Committee of Khanh Hoa province as the managing agency. Component project 2 from Km 32+000-Km 69+500 with a length of about 37.5km in Khanh Hoa and Dak Lak provinces, with a total investment of 9,818 billion VND, with the Ministry of Transport as the managing agency. Component project 3 from Km 69+500-Km 117+866 with a length of about 48.5km, with a total investment of 6,485 billion VND, with the People's Committee of Dak Lak province as the managing agency.

The Khanh Hoa-Buon Ma Thuot Expressway Construction Investment Project Phase 1 started on June 18, 2023. In the completion phase, the project is invested in the scale of an expressway, with a design speed of 80-100km/h; Phase 1 is invested in the scale of 4 limited lanes, with a roadbed width of 17m. The project has a total investment of VND 21,935 billion, with the required progress of basically completing some sections with high traffic volume by 2026 and putting them into synchronous operation in 2027.

Of the 3 component projects, Component Project 2 from Km 32+000-Km 69+500 with a length of about 37.5km in the territory of Khanh Hoa and Dak Lak provinces, managed by the Ministry of Transport, has the most complex terrain with many high hills and deep ravines, making construction work face the most difficulties.

The XL01 package alone, implemented by a consortium of contractors led by Deo Ca Group, has a total length of 11km, but includes a tunnel of 1.7km and 10 bridges of 3.6km. However, with the attention and efforts of local authorities, authorities and functional agencies; of Project Management Board 6, the Ministry of Transport and the consortium of contractors, according to the report of the Package Management Board, up to now, the contractor has handed over 10.7/11km, reaching 97%.

Currently, the contractor consortium led by Deo Ca Group has mobilized 250 personnel, 160 motorbikes and equipment, and deployed 12 construction teams including 2 teams for the Phoenix Tunnel, 5 teams for the road construction, and 5 teams for the bridge and road construction. The output is 80.5/3,083 billion VND, reaching 2.6%. To serve the construction, the construction unit must use rock drilled from the Phoenix Tunnel to spread along the road leading to the Project Management Board area and the tunneling area to make travel more convenient.

According to the plan, by December 31, 2024, the output will reach 19%, and the package is expected to be completed in June 2027. Therefore, the representative of the Package Management Board recommends that the investor and related units continue to coordinate to handle problems related to site clearance, waste disposal, material sources and power sources so that the contractor can take advantage of the sunny weather to organize construction smoothly before the rainy season comes.

Mr. Ngo Huu Khoa, Director of the XL01 Package Management Board of the Khanh Hoa-Buon Ma Thuot Expressway Construction Project, said that problems with power sources directly affected the progress of the package. To ensure progress, contractors proactively spent their own money to invest in the 22kV power line system and transformer stations to serve the construction. However, after many months of completion, the transformer stations have not been energized yet. Many machines, equipment, and material production clusters must use generators for construction, causing huge additional costs for contractors.

According to calculations, the total load demand of contractors in Component 2 Project is about 20.6Mw. However, when Dak Lak Power Company checked, the remaining load of the power supply line for the project was only about 6.4Mw... Therefore, local authorities and functional branches need to pay attention to removing difficulties and obstacles to help contractors speed up the project's construction progress.

In the last days of June, Nhan Dan Newspaper reporters were present at this "remote place" and recorded images of the construction of package XL01, Component 3 of Khanh Hoa-Buon Ma Thuot Expressway connecting the forest and the sea, implemented by the joint venture of Deo Ca Group.

Below are photos from the scene:

[Photo] In the

From Buon Ma Thuot city, reporters had to travel nearly 200km along National Highway 26 and dozens of kilometers of steep hills to reach the construction area of ​​the XL01 package, carried out by a consortium led by Deo Ca Group, located in Cu San commune, M'Drak district, Dak Lak province.

[Photo] In the

Component 2 project from Km 32+000-Km 69+500 Khanh Hoa-Buon Ma Thuot expressway with a length of about 37.5km in the territory of Khanh Hoa and Dak Lak provinces, with the Ministry of Transport as the managing agency, has the most complex terrain with many high hills and deep ravines, making construction work face the most difficulties.

[Photo] In the

Up to now, the XL01 package site handed over to the contractor is 10.7/11km, reaching 97%.

[Photo] In the

The working area of ​​the Project Management Board of package XL01 is built right at the construction site in the middle of the mountains and forests.

[Photo] In the

Motor vehicles and machinery are gathered by the contractor to serve the construction of the XL01 package of Khanh Hoa-Buon Ma Thuot expressway.

[Photo] In the

Trucks transport soil to level the Khanh Hoa-Buon Ma Thuot highway.

[Photo] In the

Contractor constructing the hill slope for the Khanh Hoa-Buon Ma Thuot expressway under package XL01, Component Project 2.

[Photo] In the

Construction contractors are drilling to build a bridge on the Khanh Hoa-Buon Ma Thuot highway.

[Photo] In the

Steel for bridge construction under package XL01 of Khanh Hoa-Buon Ma Thuot expressway is ready.

[Photo] In the

Several bridges under the XL01 package of Khanh Hoa-Buon Ma Thuot expressway are under construction.

[Photo] In the
Package XL01 of Component Project 2, Khanh Hoa-Buon Ma Thuot Expressway section through M'Dak district, Dak Lak province, is implemented by a consortium of contractors led by Deo Ca Group, passing through many high mountains.
[Photo] In the
In particular, in the XL01 package implemented by the consortium led by Deo Ca Group, there is a Phoenix tunnel with a length of 1.7km, which is the longest tunnel on the Khanh Hoa-Buon Ma Thuot highway.
[Photo] In the

After more than 1 month of opening the western tunnel and digging the tunnel, the contractor has dug about 50m long for both the right and left tunnels.

[Photo] In the

Deo Ca Group applies Austria's new NATM method to dig the Phoenix tunnel.

[Photo] In the
According to Mr. Ngo Huu Khoa, Director of the XL01 Package Management Board of the Khanh Hoa-Buon Ma Thuot Expressway Construction Project, Austria's new NATM tunneling method is both fast and has a very high level of safety in the world today.
[Photo] In the

Nhan Dan Newspaper reporters working in the Phoenix Tunnel, Khanh Hoa-Buon Ma Thuot Expressway Construction Investment Project.

[Photo] In the

Engineers operate the Phoenix tunnel boring machine, Khanh Hoa-Buon Ma Thuot highway.

[Photo] In the

The Phoenix tunnel engineers were all very young and mostly Vietnamese.

[Photo] In the

Engineers check drill bits in the Phoenix tunnel.

[Photo] In the

Engineers work in the Phoenix Tunnel.

[Photo] In the

Every 1 meter of digging, the dome must be reinforced with steel and sprayed with concrete, then continue digging the tunnel.

[Photo] In the

According to Mr. Ngo Huu Khoa, Director of the XL01 Package Management Board of the Khanh Hoa-Buon Ma Thuot Expressway Construction Project, digging the Phoenix Tunnel is convenient because the geology here is all rock in the tunnel.

[Photo] In the

Phoenix Tunnel of Khanh Hoa-Buon Ma Thuot highway seen from inside.

[Photo] In the
Mr. Ngo Huu Khoa, Director of the XL01 Package Management Board of the Khanh Hoa-Buon Ma Thuot Expressway Construction Project, introduced the area where the joint venture contractor led by Deo Ca Group was constructing.

Source: https://nhandan.vn/anh-o-noi-tham-son-cung-coc-dang-lam-cao-toc-noi-rung-va-bien-post815528.html


Comment (0)

No data
No data

Same tag

Same category

Female commandos practice parade for 50th anniversary of reunification
Overview of the Opening Ceremony of National Tourism Year 2025: Hue - Ancient Capital, New Opportunities
Helicopter squadron carrying the national flag flies over the Independence Palace
Concert Brother Overcomes a Thousand Difficulties: 'Breaking Through the Roof, Flying to the Ceiling, and Breaking Through the Heavens and Earth'

Same author

Heritage

Figure

Business

No videos available

News

Political System

Local

Product